S/N Project Name Start Date Completion Client Remark
1 Demolition of Material Offloading (MOF) 2 General Cargo Berth 2019-10 2020-09 NLNG Completed
2 Replacement of Train 1~3 Water-Cooled Heat Exchangers 2018-04 2020-03 NLNG Completed
3 K2S 2016-01 2018-02 SPDC Completed
4 Gbaran Infill (PKG 1 : Facility) 2014-04 2018-03 SPDC Completed
5 Indorama Fertilizer Plant 2013-04 2018-08 IEFCL Completed
6 Southern Swamp Gas Gathering Pipeline 2012-08 2015-02 SPDC Completed
7 Otumara Node CPF 2011-02 2015-11 SPDC Completed
8 OML 58 IPP - Early Works 2011-01 2013-04 TEPNG Completed
9 Utorogu-Ughelli East DomGas Pipeline 2010-05 2014-11 SPDC Completed
10 Ogbainbiri Flowstation Upgrade 2008-06 2014-12 NAOC Completed
11 Escravos Gas to Liquids Process Plant Project (K001) 2007-01 2013-09 CNL Completed
12 Tebidaba / Brass Oil Pipeline (Phase 1) 2006-10 2009-12 NAOC Completed
13 Gbaran Ubie IOGP – EPC for CPF, New Manifolds and Remote Locations 2006-01 2011-12 SPDC Completed
14 QIT Storage Tank 5002 Repair 2005-12 2006-12 MPNU Completed
15 Afam VI Combined Cycle Power Plant Project 2005-11 2012-03 SPDC Completed
16 EGGS 2 Gas Pipeline 2005-11 2010-06 SPDC Completed
17 Agbami FPSO 2005-08 2006-10 DSME Completed
18 EPC3 BRT Expansion 2005-01 2007-12 MPNU Completed
19 NLNG Plus Project - Train #6 2005-04 2008-07 TSKJ J/V Completed
20 EPC for 24” Gas Pipeline For Swamp Gas Gathering 2004-10 2008-09 NAOC Completed
21 QIT Crude & Condensate Heaters Interconnection Project 2003-04 2004-10 MPN Completed
22 Nigeria LNG Plus Project – Train #5 2002-11 2005-06 TSKJ J/V Completed
23 Rehabilitation of Fire Damaged NNPC Crude Oil Storage Tank (TK107) 2002-06 2004-04 NNPC Completed
24 Kwale Gas Injection Upgrading Project (Phase I) 2002-03 2004-11 NAOC Completed
25 Odidi AGG Brown Upgrade Works & EPRS 2001-10 2004-12 SPDC Completed
26 NLNG Phase 3 Gas Supply Pipeline 2001-12 2004-04 NAOC Completed
27 QIT Flare Replacement 2001-12 2003-02 NNPC + MPN Completed
28 Bongba FPSO Module Fabrication & Loadout 2001-11 2004-01 AMEC Contractors (W/A) Limited Completed
29 GTPP AFAM V278MW 2001-05 2002-03 Siemens Nigeria Completed
30 Cawthorne Channel Associated Gas Gathering Injection / Supply 2001-04 2006-06 SPDC Completed
31 QIT Tank 677 Repair 2000-08 2001-11 MPN Completed
32 EPC for 8”x18Km Obigbo to IA High Pressure Fuel Gas Supply Pipeline 2000-06 2001-10 SPDC Completed
33 Nigeria LNG Expansion Project – Train #3 2000-02 2003-06 TSKJ J/V Completed
34 Odidi Associated Gas Gathering Pipeline 1999-10 2002-06 SPDC Completed
35 Belema / Obigbo Node Cawthorne Channel AGG Pipeline 1999-01 2002-09 SPDC Completed
36 MEI Works for Obigbo Node Associated Gas Gathering Project 1999-12 2002-07 Dresser Kellogg Energy Services Completed
37 Supply and Laying of 14” Gas Pipeline 1998-10 1999-06 NAOC Completed
38 QIT PH II (Infrastruture) Project 1997-11 2000-08 MPN Completed
39 Rehabilitation of the 24”/28” Nembe Creek Trunk Line 1997-09 1999-08 SPDC Completed
40 Concrete Barge Installation 1997-09 1998-05 Chevron Completed
41 QIT Project - PH I EBS Tank Fabrication 1997-02 1997-10 MPN Completed
42 96 Swamp Flowstation 1996-12 1999-06 SPDC Completed
43 Nigeria LNG Project – Train # 1 & 2 1996-12 2000-04 TSKJ J/V Completed
44 96/97 Swamp Flowline 1996-06 2000-07 Laying of 1996/1997 Flowline in Swamp Area Pipeline : 256km / 4” & 8” Completed
45 95/96 Swamp Flowline Leak Repair 1996-06 1998-06 SPDC Completed
46 Yard Coating of Linepipe 1996-05 1997-12 SPDC Completed
47 Benin River Development Flowline & Pipeline Installation Works 1995-10 1996-05 Chevron Nigeria Limited Completed
48 Shell East Swamp Flowline Replacement (Call-off Contract) 1995-09 1996-12 SPDC Completed
49 South Forcados Development Project 1995-12 1997-10 SPDC Completed
50 Emergency Pipeline Repair 1995-08 1997-06 SPDC Completed
51 Agip Swamp Flowline Project (Call-off Contract) 1995-07 1997-12 NAOC Completed
52 Swamp Flowline Construction Works 1993-09 1996-07 SPDC Completed
53 Construction Work for Flowstation Upgrading Phase II 1992-07 1996-07 SPDC Completed
54 Egwa-1 Flowstation Upgrade & Water Injection Rehabilitation 1992-08 1993-08 SPDC Completed
55 Swamp Flowline Safety Upgrade 1992-10 1993-03 SPDC Completed
56 Rail Link to Onne Port Complex 1992-08 1994-03 Nigeria Railway Corp. Completed
57 Swamp Flowstation Rehabilitation 1992-07 1993-12 SPDC Completed
58 Bonny Terminal sludge Plant Upgrade 1991-06 1992-09 SPDC Completed
59 Additional Fire Protection Work at Bonny Terminal 1990-12 1992-04 SPDC Completed
60 Dualization of Warri ~ Benin Road 1990-06 1992-12 Ministry of Works & Housing Completed
61 Refinery Crude Oil Supply Construction Works 1988-08 1990-02 SPDC Completed
62 Rehabilitation of Tank & Bundwalls at Forcados Terminal 1988-04 1988-08 SPDC Completed
63 Escravos and Warri Oil Storage Tanks 1988-02 1990-04 NNPC Completed
64 Escravos-Lagos Gas Pipeline 1988-02 1990-08 NNPC Completed
65 Nitrogenous Fertilizer Plant M&E Erection Work 1985-02 1987-06 National Fertilizer Company of Nigeria Ltd. Completed
66 NNPC Petrochemical PH I (Polypropylene Plant) M&E Erection Works 1984-12 1988-04 NNPC Completed
67 NNPC Petrochemical PH I (Carbon Black & H.F. Alkylation) Plant 1983-10 1986-01 NNPC Completed
68 NNPC Petrochemical PH I (Polypropylene Plant) Civil Works 1983-04 1986-12 NNPC Completed
69 Construction of Productive Borehole (Lot 58) 1983-01 1983-12 Ministry of Water Resources Completed
70 Indorama 2nd Fertilizer Plant 2018-05 2020-04 IEFCL Completed