Client: SPDC | |
Start: 2014-04 | |
Completion: 2018-03 | |
Location: Gbaran, Ubie Bayelsa State |
In April 2014, Daewoo Nigeria Limited was awarded the Gbaran Infill Package-1 Facility project contract by Shell Petroleum Development Company of Nigeria (SPDC).
Project Scope:
This project covered the Engineering, Procurement & Construction (EPC) works for Upgrading the existing GBU Central Processing Facilities (CPF) & Remote Facilities and The Installation of New Facilities at Gbaran/ Ubie Fields in Bayelsa State.
This project was completed and commisioned in March, 2018