Client: NLNG | |
Start: 2018-04 | |
Completion: 2020-03 | |
Location: Bonny Island |
In April 2018, Daewoo Engineering & Construction Nigeria Limited was awarded the Replacement of Water-Cooled Heat Exchangers project for Train 1, 2 & 3 respectively by the Nigerian Liquified Natural Gas (NLNG).
Project Scope:
The project covered the Replacement and installation works for eight (8) Units of the Heat Exchangers for each of the Train 1, 2 & 3 respectively at the Bonny Terminal, Bonny Island, Rivers State.
This project was completed and commissioned in March, 2020.