Client: NAOC
Start: 2008-06
Completion: 2014-12
Location: Ogbainbiri/ Bayelsa State

Ogbainbiri Flowstation Upgrade

In June 2008, Daewoo Nigeria Limited was awarded the Ogbainbiri Flowstation Upgrade project contract by Nigerian Agip Oil Company (NAOC).

Project Scope:

This project covered the Engineering, Procurement & Construction (EPC) works for the upgrading of the Oil & Gas Flowstation with production capacity of Gas 195 MMscf/d and Oil 45,000 bpd at Ogbainbiri Flowstation, Ogbainbiri, Bayelsa State

This project was completed and commissioned in December, 2014.