Client: MPNU
Start: 2005-01
Completion: 2007-12
Location: Bonny Island/ Rivers State

EPC3 BRT Expansion

In January 2005, Mobil Producing Nigeria Unlimited (MPNU) awarded the Bonny Terminal BRT Expansion Project to Daewoo Nigeria Limited.

Project Scope:

The contract scope covered for the Expansion Works for the Existing Bonny Terminal from Site Development to the completion of 65,000 bbl/d Fraction Train & associated Utilities and 300,000 bbl/d pentane Plus Storage Tank at Bonny Terminal, Bonny Island, Rivers State.

The project was completed and commissioned in December, 2012.