Client: CNL
Start: 2007-01
Completion: 2013-09
Location: Escrasvos/ Delta State

Escravos Gas to Liquids Process Plant Project (K001)

In January 2007, Daewoo Nigeria Limited was awarded the Escravos Gas to Liquids Process Plant (K001) project contract by Chevron Nigeria Limited (CNL).

Project Scope:

The project scope covered the Engineering, Procurement & Construction (EPC) works for the implementation of the process plant at the Escravos Terminal, Delta State.comprising

- Civil Works

- Mechanical Works

- Instrumentation Works 

- Electrical Works

- FIR Proofing for the Process Plant

The Escravos Gas to Liquids Process Plant (K001) have production capacity of 320 MMscf/d comprising

- Diesel 22,100 bpd,

- naphtha 10,300 bpd &

- LPG 900 bpd

This project was completed and commissioned in September, 2013.