Client: SPDC | |
Start: 1999-01 | |
Completion: 2002-09 | |
Location: Belema |
In January 1999, Shell Petroleum Development Company of Nigeria. (SPDC) awarded the Belema / Obigbo Node Cawthorne Channel Associated Gas Gathering Pipeline project to Daewoo Nigeria Limited.
Project Scope:
This contract scope covered for the Engineering, Procurement & Construction (EPC) of the Belema Swamp Gas Injection Pipeline System at Belema/ obigbo Node.
Pipeline : 6” x 12.50km
8” x 22.04km
16” x 15.58km
The project was completed and commissioned in September, 2002.