S/N Project Name Start Date Completion Client Remark
1 Maintenance Services For Quick-Fix Repairs of KRPC (Kaduna Refining & Petrochemicals Company) 2023-03 2025-03 KADUNA REFINING AND PETROCHEMICAL COMPANY LIMITED (NNPC LTD) Ongoing
2 Maintenance Services For Quick-Fix Repairs of WRPC (Warri Refining & Petrochemicals Company) 2022-11 2024-12 WARRI REFINING AND PETROCHEMICAL COMPANY LIMITED (NNPC LTD) Ongoing
3 NLNG Train 7 2020-05 2026-06 NLNG Ongoing
4 Gbaran Phase 3A 2014-05 2024-11 SPDC Ongoing
5 Replacement of Train 1~3 Water-Cooled Heat Exchangers 2018-04 2020-03 NLNG Completed
6 K2S 2016-01 2018-02 SPDC Completed
7 Gbaran Infill (PKG 1 : Facility) 2014-04 2018-03 SPDC Completed
8 Otumara Node CPF 2011-02 2015-11 SPDC Completed
9 Ogbainbiri Flowstation Upgrade 2008-06 2014-12 NAOC Completed
10 Escravos Gas to Liquids Process Plant Project (K001) 2007-01 2013-09 CNL Completed
11 Gbaran Ubie IOGP – EPC for CPF, New Manifolds and Remote Locations 2006-01 2011-12 SPDC Completed
12 NLNG Plus Project - Train #6 2005-04 2008-07 TSKJ J/V Completed
13 Nigeria LNG Plus Project – Train #5 2002-11 2005-06 TSKJ J/V Completed
14 Bongba FPSO Module Fabrication & Loadout 2001-11 2004-01 AMEC Contractors (W/A) Limited Completed
15 Nigeria LNG Expansion Project – Train #3 2000-02 2003-06 TSKJ J/V Completed
16 Nigeria LNG Project – Train # 1 & 2 1996-12 2000-04 TSKJ J/V Completed