Client: NNPC
Start: 1984-12
Completion: 1988-04
Location: Warri/ Delta State

NNPC Petrochemical PH I (Polypropylene Plant) M&E Erection Works

In December 1984, Daewoo Nigeria Limited was awarded the NNPC Petrochemical PH I (Polypropylene Plant) M&E Erection Project by the Nigerian National Petroleum Corporation (NNPC).

This contract scope covered the following areas for (Polypropylene Plant) project of the NNPC Petrochemical PH I (Polypropylene Plant) in Warri Delta State.

- Equipment Erection : 2,500 ton
- Tanks Fabrication & Erection : 1,500 ton
- Piping : 1,600 ton
- Painting & Insulation
- Erection & Instrument Works

The project was completed and commissioned in April, 1988.