Client: Chevron Nigeria Limited
Start: 1995-10
Completion: 1996-05
Location: Warri/ Delta State

Benin River Development Flowline & Pipeline Installation Works

In October 1995, Chevron Nigeria Limited (CNL) awarded the Benin River Development Flowline & Pipeline project to Daewoo Nigeria Limited.

Project Scope:

This for the Installation of 4,500 tons of Prefabricated Concrete Barge and 4” & 8” x 21.4km pipelines for the Benin River Flowstation Field in Warri Delta State.

The project was completed and commissioned in May, 1996.