Client: SPDC
Start: 1988-04
Completion: 1988-08
Location: Forcados/ Bayelsa State

Rehabilitation of Tank & Bundwalls at Forcados Terminal

In April 1988, Daewoo Nigeria Limited was awarded the Rehabilitation of Tank  & Bundwalls at Forcados Terminal by the Shell Petroleum Development Company of Nigeria (SPDC).

Project Scope:

This contract scope covered for the Site Preparation measuring 20,339m2, Asphalting measuring 20,400m2 and Rehabilitation of Tank Pad & Bundwalls for Ten (10) Storage Tanks, Two (2) Sludge Tanks, Fuel Tank at Forcados Terminal, Delta State.

The project was completed and commissioned in August, 1988.