Client: INDORAMA ELEME FERTILIZER AND CHEMICALS LIMITED (IEFCL) | |
Start: 2023-08 | |
Completion: 2026-07 | |
Location: ELEME, RIVERS STATE |
Project Overview
Indorama contracted Daewoo E & C Nigeria Limited, to build the Urea Fertilizer Train III, known as Line 3, at Indorama Eleme Fertilizer and Chemicals Limited (IEFCL), in Eleme, Rivers State, Nigeria. Line 3 is designed to build upon the technologies and knowledge gained from the development and operation of Line 1 and Line 2, featuring similar technology and capacity on August 20, 2023.
The creation of Line 3 will raise the present urea production capacity from 2.8 MMTPA to 4.2 MMTPA. The Line 3 plant will contain a 2,300 Metric Tons Per Day (MTPD) capacity for ammonia, a 4,000 MTPD urea facility, steam, cooling tower, water treatment, product handling, power, nitrogen, plant air and instrument air, passive and active firefighting systems, along with product storage and material handling facilities.
Daewoo E & C Nigeria Limited commenced project execution on August 1 2023 at Indorama Eleme Fertilizer and Chemicals Limited (IEFCL), in Eleme, Rivers State. The project is expected to run for thirty-eight (38) months from the date of Award.
Project Objectives
The project development objective is the expansion of the Company’s urea plant from 2.8 MMTPA to 4.2 MMTPA.
Project Scope
The Line 3 plant will contain a 2,300 Metric Tons Per Day (MTPD) capacity for ammonia, a 4,000 MTPD urea facility, steam, cooling tower, water treatment, product handling, power, nitrogen, plant air and instrument air, passive and active firefighting systems, along with product storage and material handling facilities.