Client: KADUNA REFINING AND PETROCHEMICAL COMPANY LIMITED (NNPC LTD)
Start: 2023-03
Completion: 2025-03
Location: Kaduna

Maintenance Services For Quick-Fix Repairs of KRPC (Kaduna Refining & Petrochemicals Company)

On February 2 2023, the Nigerian National Petroleum Corporation (NNPC) awarded to Daewoo Engineering & Construction Nigeria Limited the contract for the Maintenance Services for Quick-Fix Repairs for Kaduna Refining & Petrochemical Company (KRPC).

 

Daewoo E & C Nigeria Limited commenced project execution on March 1 2023 at KRPC,Kaduna Refinery, Kaduna State. The project is expected to run for twenty-four (24) months from the date of Award.

 

Project Scope

The project will take a total of 24 months for completion. Construction schedules for Packages 1 and 2 have been finalized, but Package 3 construction will be carried out under consultations with and approval from the client in the future.